Put a task on a milestone so it counts toward the plan, or point it at a related project, from the Plan group of the task panel.
Two rows in the Plan group of the task panel connect a task to other work. Milestone puts the task on a checkpoint in its project's plan, so finishing the task moves the milestone forward. Related project points the task at one other project, so you can jump there from the task.
Open a task, then find both rows near the top of the Plan group. In Focused, a row shows its value on one line (a milestone's name, or "N milestones" when there are several) and an empty one waits under More properties. See The task panel.
Milestone#
A milestone finishes when the tasks linked to it do. You can link a task from the milestone's card, as Build a plan with milestones describes, or from the task itself.
- Open the task and find Milestone in the Plan group.
- Choose Add to a milestone… and pick one. The list holds the milestones of the task's own project that the task is not on yet.
- To take the task off a milestone, press the X on that milestone's chip.
A task can be on several milestones, and each shows as a chip.
Adding a task to a milestone needs the same planning access as milestones themselves. Where it is locked, Yipadoo refuses the change.
What cannot be linked#
- A repeating task. The row says "A recurring task can't be on a milestone."
- A subtask. A subtask counts through its top-level task. It shows that task's milestones marked "via parent", and the row says "None. Set it on the top-level task." when there are none. Link the top-level task instead.
- A task in a project with no milestones. The row says "No milestones in this project."
Related project#
Related project points a task at one project outside its own. The task stays in its own project.
- Open the task and find Related project in the Plan group.
- Choose a project from the list. It holds every project you can read and that is not archived, except the task's own project and the Inbox. A team project or a nested project has its place written after its name, such as the workspace it belongs to.
- To remove the link, choose No related project.
In Full, a linked task shows a link icon and the project's name on its row. Click the name to open that project. If you cannot read the linked project, the task shows "Unavailable project" and the link opens nothing. See Read a task row.